Enbridge Inc. must go through a lengthy process seeking Michigan energy regulators’ approval to build a $500 million tunneled pipeline that would replace the four-mile segment of the company’s Line 5, which lies on the Straits of Mackinac lake bed between Lake Michigan and Lake Huron, a state commission ruled Tuesday.

The Michigan Public Service Commission denied Enbridge a declaratory ruling that it need not secure additional approval from state energy regulators to build the tunneled pipeline replacement.

It rejected the Canadian energy giant’s request by ruling that the tunneled line counts as a new construction or extension of facilities,...